Tuesday, July 24, 2012
Fixing Stage - Week 12
Render has started.
Photos taken on 23 June 2012
front view with render
side view with render
render
gutter and fascia in Colorbond Jasper
downpipe in Colorbond Jasper
entry to living area
Fixing Stage - Week 11
Fixing Stage has started. Architraves have been installed.
Photos taken on 16 June 2012
back view
side view
living area wall
hallway architraves
Lock Up Stage - Week 10
Plastering has commenced.
Photos taken on 09 June 2012
rumpus
living/dining area
masters bedroom
front view of the house
Lock Up Stage - Week 9
Plumbing, electricals and heating installed
Photos taken on June 2
front view
unpainted doors
heating roughin
masters bedroom window
Lock Up Stage - Week 8
Brick work is almost complete
Taken on 26 May 2012
side view
front view
Lock Up Stage - Week 7
Brick work has started
Taken on 19 May 2012
view from the side
front view
side view
back view
brick work has started
bricks delivered
boral brushwood bricks
garage
bricks from inside of the garage
rumpus
Lock Up Stage - Week 6
Lock Up Stage has started, roof installation has commenced
Taken on 12 May 2012
roof installation
roof tiles delivered
portico
living room frame and windows
found this in the powder room area... hmm not sure if it's acceptable
garage
Sunday, May 6, 2012
Frame Stage - Week 5
Framing at the first level.
Taken on 05 May 2012
Front View
Side View
Rear View
Frame Stage - Week 4
Framing at the ground level
Taken on 28 April 2012
Front View
Side View
Frame Stage - Week 3
Frame Stage started. Taken on 21 April 2012
windows delivered
side view
portico
Base Stage - Week 2
Base Stage Started. Taken on 14 April 2012.
Side View
Front View
Garage is the biggest room of the house lol