Tuesday, July 24, 2012
Lock Up Stage - Week 6
Lock Up Stage has started, roof installation has commenced
Taken on 12 May 2012
roof installation
roof tiles delivered
portico
living room frame and windows
found this in the powder room area... hmm not sure if it's acceptable
garage
Sunday, May 6, 2012
Frame Stage - Week 5
Framing at the first level.
Taken on 05 May 2012
Front View
Side View
Rear View
Frame Stage - Week 4
Framing at the ground level
Taken on 28 April 2012
Front View
Side View
Frame Stage - Week 3
Frame Stage started. Taken on 21 April 2012
windows delivered
side view
portico
Base Stage - Week 2
Base Stage Started. Taken on 14 April 2012.
Side View
Front View
Garage is the biggest room of the house lol